TM 1-4920-433-13&P
0037 00
INSTALLATION
CABINETS (A) AND (B) HARDWARE
1.
Install two bolts (Figure 1, Item 4), two lock washers (Figure 1, Item 5), and two lat washers (Figure 1, Item
6) securing cabinets (A) (Figure 1, Item 1) and (B) (Figure 1, Item 2) to shelter wall.
2.
Install four bolts (Figure 1, Item 4), four lock washers (Figure 1, Item 5), and four lat washers (Figure 1, Item
6) securing two cabinet brackets (Figure 1, Item 3) to shelter loor.
Torque bolts (Figure 2, Item 4) 160-190 in. lbs.
3.
4.
Install drawers, slides, and shelves as necessary IAW (WP 0036 00, Drawers, Slides, And Shelves,
INSTALLATION ).
5.
Install kick plate IAW (WP 0036 00, Kick Plate, INSTALLATION ).
INSPECTION OF INSTALLED ITEMS
CABINETS (C) AND (D) HARDWARE
Figure 2.
Cabinets (C) and( D) Hardware.