TM 1-4920-433-13&P
PREPARATION FOR STORAGE OR SHIPMENT
1.
Refer to TM 10-5411-201-14, Operator, Organizational, Direct Support, and General Support Mainte-
nance for Shelter, Tactical, Expandable, One-Sided, if necessary.
2.
Refer to shop equipment TMs and manufacturer supplied operating manuals for proper storage and
shipment instructions.
3.
Inspect the shelter for the following and ensure that:
a.
All circuit breakers and switches are in OFF position.
b.
Circuit breaker panel door is secured.
c.
Lights and receptacle outlets are properly stowed.
d.
Jacks are secured in the appropriate stowage position.
e.
Roof struts are secured.
f.
Stop plate in the load balancer is in down position and secured with pin.
g.
Foot bolt and chain bolt are secured.
h.
Camlock pin is engaged in hole on corner post.
i.
All shelter components are properly secured.
j.
Protective dust caps are secure on power entry panel receptacles and binding posts are tightened.
k.
All doors are secured.
4.
Store shelter in a dry area or a designated supply facility. If stored outside in humid conditions, perform
a quarterly inspection to ensure moisture is not inside shelter.
0001 00-2