b. Position storage chest (1) in mounting bracket (2).
2-6. Storage of Hardware.
Care must be taken to ensure that proper hardware is used to secure
equipment for transport. Lack of correct hardware could cause exten-
sive damage to equipment or the shelter when shop is moved.
a. All hardware removed from equipment will be collected and placed in cotton mailing bags (see item 3, App
E). Bags are stored in the shop storage chest until shelter is to be moved and equipment bolted to the floor.
2-7. Checking Shelter Level.
Once all equipment is in the recommended operational position recheck leveling of
shelter. Use procedures in TM 10-5411-201-14 to verify and adjust level. Correct adjustment is essential to ensure
proper operation of machine tools, doors and access panels. The Tool Crib Shop is now operational.
2-8.
a.
b.
c.
SECTION Ill. PREPARING SHOP FOR SHIPMENT OR STORAGE
Recover and Inspect Equipment Hardware.
Remove shop storage chest from mounting brackets.
Care must be taken to ensure that proper hardware is used to secure
equipment for transport. Lack of correct hardware could cause exten-
sive damage to equipment or the shelter when shop is moved.
Recover cotton mailing bags with hardware from shop storage chest.
Inspect hardware for damage or missing parts.
2-19