UNUSUAL ENVIRONMENT/WEATHER CONTINUED
OPERATION IN HIGH WINDS CONTINUED
Figure 3.
Loops and Clamps Installation.
3.
Drive each of six loop and clamp ground anchors into ground approximately 3 feet (91.5 cm) deep, and as
close as possible to shelter attaching points, at locations indicated.
4.
Set each ground anchor by forming a loop in cable end and secure loop with clamp.
0033 00-3