TM 9-4933-223-13&P
NOTE
12 TWO BRACKETS (19) AND WALL
SHELF (20). Position together.
Steps 12 thru 15 pertain to
reassembly
of
one
wall
13 TWO SCREWS (21), TWO FLAT
shelving. There are four wall
WASHERS (22), AND TWO NUTS (23).
shelvings mounted on the
Install on wall shelf (20) and bracket
shelter walls; the other three are
(19).
reassembled in the same
manner.
14 TWO BRACKETS (19). Hold in position
so that holes line up with blind inserts in
shelter wall.
15 FOUR FLAT WASHERS (24) AND
FOUR SCREWS (25). Install in shelter
wall.
NOTE
Three tiedown straps (26) are used to tie the cable coil to
the shelter floor, four tiedown straps (27) are used to tie the
sorting file and wall shelvings to tables, and four tiedown
straps (28) are used to tie stools and equipment storage
chest to floor.
16 THREE TIEDOWN STRAPS (26), FOUR TIEDOWN STRAPS (27), R AND
FOUR TIEDOWN STRAPS (28). Place in storage.