Figure 6. Connecting Main Power Cable to Shelter.
INSTALL LIGHTING

Maintenance Manual For Production/ Quality Control Shop Part No. 1036659 And Part No. Sc4920-99-Cla66
Page Navigation
  35    36    37    38    39  40  41    42    43    44    45  
img
TM 1-4920-440-13&P
0006 00
CONNECTING MAIN POWER CABLE - CONTINUED
Figure 7.
Connecting Main Power Cable to PDB.
10. Remove protective dust cap from receptacle at PDB (Figure 7, Item 1).
11. Remove protective dust cap (Figure 7, Item 3) from male power connector (Figure 7, Item 2).
12. Insert male power connector (Figure 7, Item 2) into receptacle at PDB (Figure 7, Item 1) and secure with lock
ring (Figure 7, Item 4).
13. Move circuit breaker located on the PDB from OFF to ON.
14. Move main and other circuit breakers in circuit breaker panel from OFF to ON.
END OF WORK PACKAGE
0006 00-7/8 blank