TM 10-5411-236-13&P
0005 00
WARNING
Do not allow the system to swing if using overhead lift. Always ensure an appropriate
sling is used in the lift. Always use properly sized forklift, crane-lifting device. Always
use appropriate blocking/bracing in conjunction with proper MHE when working under
the container. Failure to comply with these safety measures could cause serious injury
or damage to equipment.
Installation
1.
Using proper MHE (properly rated forklift or crane), lift the ASLMS container approximately
12-inches off the ground at the FPU-8 end to allow access to the rear frame assembly of the
container.
2.
Safely block/brace both sides of container with suitable safety support material near rear
before proceeding.
3.
Position roller assembly, which includes pins, so that the roller extends outside the container
frame (lanyard retaining ring with lanyards and linchpins facing away from the container).
4.
Person number one fits the roller saddle to the underside of the container frame and aligns
the two pinning holes.
5.
Second person inserts the two pins through the aligned holes to attach roller assembly to
container frame.
6.
Secure the two pins in place using the four linchpins attached to the exterior side of the roller
assembly.
7.
Repeat process for other roller.
Removal
1. Using proper MHE (properly rated forklift or crane), lift the ASLMS container approximately 12-inches
off the ground at the FPU-8 end to allow access to the rear frame assembly of the container.
2. Safely block/brace both sides of container with suitable safety support material near rear before
proceeding.
3. Remove the four linchpins from the exterior side of the roller assembly.
4. Remove the two pins holding the roller assembly to the container frame.
5. Remove roller assembly from container frame.
0005 00-17
Change 1