TM 1-4920-440-13&P
0053 00
INSTALLATION CONTINUED
Figure 11.
Air Feed-thru Connector Assembly.
2.
Install air feed-thru connector assembly (Figure 11, Item 1) from outside of shelter with long end through hole.
Figure 12.
Air Feed-thru Connector Assembly.
3.
Install all but one screw (Figure 12, Item 1), and have an assistant install two lat washers (Figure 12, Item 2),
two lock washers (Figure 12, Item 3), and two nuts (Figure 12, Item 4) inside of shelter and secure.
4.
Replace one lanyard (Figure 12, Item 5) on outside of shelter and install screw (Figure 12, Item 1).
5.
Have an assistant install lat washer (Figure 12, Item 2), lock washer (Figure 12, Item 3), second lanyard
(Figure 12, Item 5), and nut (Figure 12, Item 4) on inside of shelter.
6.
Tighten screws (Figure 12, Item 1).
END OF WORK PACKAGE