TM 1-4920-435-13&P
0042 00
INSTALLATION CONTINUED
d.
Measure from right side of work surface (Figure 6, Item 7) towards left 12.00 inches and from front of
work surface (Figure 6, Item 7) towards back 16.25 inches and mark measurement (Figure 6, Item 14).
e.
Center punch and drill two 1/2 inch holes (Figure 6, Item 11 and 12) through work surface (Figure 6, Item
7) and cabinet (E) (Figure 6, Item 10).
f.
Center punch and drill two 1/2 inch holes (Figure 6, Item 13 and 14) through work surface (Figure 6, Item
7) and cabinet (F) (Figure 6, Item 9).
9.
Install hardware attaching cabinet (D) (Figure 6, Item 4), cabinet (E) (Figure 6, Item 10) and cabinet (F)
(Figure 6, Item 9) to shelter loor IAW WP 0043 00, Cabinets (D), (E), and (F) Hardware, INSTALLATION.
10. Install drawers, slides, and shelves as necessary (Drawers, Slides, And Shelves, INSTALLATION).
11. Install kick plate (Kick Plate, INSTALLATION).
END OF WORK PACKAGE
0042 00-15/16 blank