TM 1-4920-436-13&P
0034 00
INSPECTION OF INSTALLED ITEMS CONTINUED
SHELF CABINET (D) CONTINUED
1. Inspect cabinet assembly and work surface (Figure 5) for damage. Replace as necessary.
2.
Inspect all cabinet assembly hardware (Figure 5, Item 1, 2, 3, 4, 8 and 9) for rust, cracks and rounded heads.
Replace as necessary.
REMOVAL
1.
Remove kick plate IAW (Kick Plate , REMOVAL).
2.
Remove drawers, slides, and shelves as necessary IAW (Drawers, Slides, And Shelves, REMOVAL).
3.
Remove hardware attaching shelf cabinet (D) (Figure 5, Item 6) to shelter loor IAW WP 0035 00, Cabinet E
and F Hardware, REMOVAL.
4.
Remove eight lag bolts (Figure 5, Item 1), eight lock washers (Figure 5, Item 2), six large lat washers (Figure
5, Item 3), and two small lat washers (Figure 5, Item 4) detaching work surface (Figure 5, Item 5) from cabinet
(D) (Figure 5, Item 6).
5.
Remove work surface (Figure 5, Item 5) from top of cabinet (D) (Figure 5, Item 6).
6.
Remove four bolts (Figure 5, Item 8), eight lat washers (Figure 5, Item 4), four lock washers (Figure 5, Item
2), and four nuts (Figure 5, Item 9) detaching two cabinet brackets (Figure 5, Item 7) from cabinet (D) (Figure
5, Item 6).
REPAIR OR REPLACEMENT
1.
If cabinet brackets (Figure 5, Item 7) can be repaired by welding, weld damaged area IAW TM 1-1500-204-23.
Repair must not interfere with form, it, or function of cabinet brackets (Figure 5, Item 7).
2.
Paint repaired cabinet brackets (Figure 5, Item 7) IAW WP 0056 00, Figure 1.
INSTALLATION
1.
If a new shelf cabinet (D) (Figure 5, Item 6) must be installed:
a.
On top left side of shelf cabinet (D) (Figure 5, Item 6), measure from front existing bolt hole toward back
12.25 inches and mark measurement. Measure from side of cabinet 1.625 inches to new placement
mark and mark measurement (Figure 5, Item 13).
b.
On top back side of shelf cabinet (D) (Figure 5, Item 6), measure from left existing bolt hole toward right
13 inches and mark measurement. Measure from side of cabinet 1.625 inches to new placement mark
and mark measurement (Figure 5, Item 10).
c.
On top right side of shelf cabinet (D) (Figure 5, Item 6), measure from front existing bolt hole toward back
12.25 inches and mark measurement. Measure from side of cabinet 1.625 inches to new placement
mark and mark measurement (Figure 5, Item 11).
d.
On top front side of shelf cabinet (D) (Figure 5, Item 6), measure from left existing bolt hole toward right
13 inches and mark measurement. Measure from side of cabinet 1.625 inches to new placement mark
and mark measurement (Figure 5, Item 12).
e.
Center punch and drill four 13/32 inch holes.
2.
If a new work surface (Figure 5, Item 5) must be installed:
a.
Position work surface (Figure 5, Item 5), inished side up, on top of shelf cabinet (D) (Figure 5, Item 6).
b.
Ensure work surface (Figure 5, Item 5) is lush with back side of cabinet with a two inch over hang on the
front side of cabinet. Work surface (Figure 5, Item 5) should over hang 15.00 inches on left and right side
of cabinet
c.
On inside of shelf cabinet (D) (Figure 5, Item 6), mark eight hole placements in top of cabinet on non-
inished side of work surface (Figure 5, Item 5).
d.
After eight hole placement marks have been made, lip work surface (Figure 5, Item 5) over with non-
inished side up.
0034 00-11