TM 1-4920-438-13&P
0034 00
RAISING HINGED FLOOR - CONTINUED
will remain under tension. DO NOT attempt to remove cables if support cables are not secure.
Removing support cables while under tension could cause SERIOUS INJURY to personnel.
Figure 7.
Load Balancers Slide Stops, Upper Position.
1.
Remove lockout pins (Figure 7, Item 4) from lower position on both load balancers (Figure 7, Item 3).
2.
Open slide stops (Figure 7, Item 1) against support cables (Figure 7, Item 2) on both load balancers (Figure
7, Item 3).
3.
Replace lockout pins (Figure 7, Item 4) in upper position on both load balancers (Figure 7, Item 3).
0034 00-7