TM 1-4920-436-13&P
0035 00
REMOVAL CONTINUED
CABINETS A AND B HARDWARE CONTINUED
3.
Remove four bolts (Figure 1, Item 4), four lock washers (Figure 1, Item 5), and four lat washers (Figure 1,
Item 6) detaching two cabinet brackets (Figure 1, Item 3) from shelter loor.
4.
Remove three bolts (Figure 1, Item 4), three lock washers (Figure 1, Item 5), and three lat washers (Figure
1, Item 6) detaching cabinets (A) and (B) (Figure 1, Item 1, 2, and 7) from shelter wall.
INSTALLATION
CABINETS A AND B HARDWARE
1.
Install three bolts (Figure 1, Item 4), three lock washers (Figure 1, Item 5), and three lat washers (Figure 1,
Item 6) securing cabinets (A) and (B) (Figure 1, Item 1, 2, and 7) to shelter wall.
Torque bolts (Figure 1, Item 4) 160-190 in. lbs.
2.
3.
Install four bolts (Figure 1, Item 4), four lock washers (Figure 1, Item 5), and four lat washers (Figure 1, Item
6) securing two cabinet brackets (Figure 1, Item 3) to shelter loor.
Torque bolts (Figure 1, Item 4) 160-190 in. lbs.
4.
5.
Install slides, drawers, and shelves as necessary (WP 0034 00, Drawers, Slides, And Shelves,
INSTALLATION ).
6.
INSPECTION OF INSTALLED ITEMS
CABINETS C AND D HARDWARE
Figure 2.
Cabinets C and D Hardware.
Inspect cabinet assembly integration hardware (Figure 2) for rust, cracks and rounded heads. Replace as nec-
essary.
0035 00-3