TM 1-4920-438-13&P
0040 00
INSPECTION OF INSTALLED ITEMS
4 DRAWER CABINET (C) AND 4 DRAWER CABINET (D)
Figure 4.
Cabinet (C) and Cabinet (D).
1.
Inspect cabinet assembly and work surface (Figure 4) for damage. Replace as necessary.
2.
Inspect all cabinet assembly hardware (Figure 4, Item 2, 3, 4, 14, 15 and 17) for rust, cracks and rounded
heads. Replace as necessary.
REMOVAL
4 DRAWER CABINET (C) AND 4 DRAWER CABINET (D)
1.
Remove kick plate (Kick Plate , REMOVAL).
2.
Remove drawers, slides, and shelves as necessary (Drawers, Slides, And Shelves, REMOVAL).
3.
Remove hardware attaching cabinet (C) (Figure 4, Item 7) and cabinet (D) (Figure 4, Item 6) to shelter wall
4.
Remove four lag bolts (Figure 4, Item 4), four lock washers (Figure 4, Item 3), and four lat washers (Figure 4,
Item 15) detaching work surface (Figure 4, Item 13) from cabinet (C) (Figure 4, Item 7 and cabinet (D) (Figure
4, Item 7).
0040 00-7