INSTALLATION CONTINUED
CABINETS A AND B HARDWARE CONTINUED
4.
Install slides, drawers, and shelves as necessary (WP 0040 00, Drawers, Slides, And Shelves,
INSTALLATION ).
5.
INSPECTION OF INSTALLED ITEMS
CABINETS C AND D HARDWARE
Figure 2.
Cabinets C and D Hardware.
Inspect cabinet assembly integration hardware (Figure 2) for rust, cracks and rounded heads. Replace as nec-
essary.
REMOVAL
CABINETS C AND D HARDWARE
1.
2.
Remove slides, drawers, and shelves as necessary (WP 0040 00, Drawers, Slides, And Shelves, REMOVAL
).
3.
Remove four bolts (Figure 2, Item 4), four lock washers (Figure 2, Item 5), and four lat washesr (Figure 2,
Item 9) detaching two cabinet brackets (Figure 2, Item 3) from shelter loor.
4.
Remove four bolts (Figure 2, Item 4), four lock washers (Figure 2, Item 5), and four lat washers (Figure 2,
Item 6) detaching cabinet (C) (Figure 2, Item 1) and cabinet (D) (Figure 2, Item 2) from shelter wall.
INSTALLATION
CABINETS C AND D HARDWARE
1.
Install four bolts (Figure 2, Item 4), four lock washers (Figure 2, Item 5), and four lat washers (Figure 2, Item
6) securing cabinet (C) (Figure 2, Item 1) and cabinet (D) (Figure 2, Item 2) to shelter wall.
0041 00-3