b.
Ensure work surface (Figure 7, Item 5) is lush with back side of cabinet with a two inch over hang on the
front side of cabinet. Work surface (Figure 7, Item 5) should over hang 15.00 inches on left and right side
of cabinet
c.
On inside of cabinet (G) (Figure 7, Item 6), mark eight hole placements in top of cabinet on non-inished
side of work surface (Figure 7, Item 5).
d.
After eight hole placement marks have been made, lip work surface (Figure 7, Item 5) over with non-
inished side up.
e.
On non-inished side of work surface (Figure 7, Item 5) at eight marked hole placements, center punch
and drill eight 5/16 inch holes to a depth of 3/4 inch.
f.
Return work surface (Figure 7, Item 5) inished side up, on top of cabinet (G) (Figure 7, Item 6).
g.
Align bolt holes in work surface (Figure 7, Item 5) with bolt holes on top of cabinet (G) (Figure 7, Item 6).
h.
Install lag eight bolts (Figure 7, Item 1), eight lock washers (Figure 7, Item 2), six large lat washers
(Figure 7, Item 3), and two small lat washers (Figure 7, Item 4) securing work surface (Figure 7, Item 5)
to cabinet (G) (Figure 7, Item 6).
3.
Install four bolts (Figure 7, Item 11), eight lat washers (Figure 7, Item 4), four lock washers (Figure 7, Item 2),
and four nuts (Figure 7, Item 12) securing two cabinet brackets (Figure 7, Item 10) into cabinet (G) (Figure 7,
Item 6).
4.
If a new cabinet (G) (Figure 7, Item 6) has been installed:
a.
Use holes (Figure 7, Item 7 through 9) of existing work surface (Figure 7, Item 5) to determine drill bit
sizes.
b.
Match drill holes (Figure 7, Item 7 through 9) of work surface (Figure 7, Item 5) through cabinet (G)
(Figure 7, Item 6).
5.
If a new work surface (Figure 7, Item 5) has been installed and/or a new work surface and cabinet (G) (Figure
7, Item 6) has been installed:
a.
Position back right corner of machinist s vise 24.31 inches from right side of work surface (Figure 7, Item
5) and 9.50 inches from back of work surface (Figure 7, Item 5).
b.
Mark three placement holes (Figure 7, Item 7 through 9). Set aside machinist s vise.
c.
Center punch and drill three 1/2 inch holes through work surface (Figure 7, Item 5) and cabinet (G)
(Figure 7, Item 6).
6.
Install hardware attaching cabinet (G) (Figure 7, Item 6) to shelter loor IAW WP 0041 00, Cabinet E, F and
G Hardware, INSTALLATION.
7.
Install drawers, slides, and shelves as necessary (Drawers, Slides, And Shelves, INSTALLATION).
8.
Install kick plate (Kick Plate, INSTALLATION).