TM 1-4920-438-13&P
FIELD MAINTENANCE
POWER TRAIN SHOP
MAINTENANCE INSTRUCTIONS FOR MACHINIST VISE AND HARDWARE
INITIAL SETUP:
Personnel Required
Tools and Special Tools
General Mechanics Tool Kit
CMF 15 Series (6)
Equipment Condition
Functional
NOTE
During installation of components same hardware should be used so as to maintain original
integrity of shop set.
INSPECTION OF INSTALLED ITEMS
Figure 1.
Machinist Vise.
1.
Inspect machinist vise (Figure 1) for damage. Replace as necessary.
2.
Inspect machinist vise hardware (Figure 1, Item 2 through 6) for rust, cracks and rounded heads. Replace
as necessary.
REMOVAL
Remove three bolts Figure 1, Item 2), three upper lat washers (Figure 1, Item 3), three lower lat washers (Figure
1, Item 4), three lock washers (Figure 1, Item 5) and three nuts (Figure 1, Item 6).