0038 00
TM 1-4920-441-13&P
INSTALLATION CONTINUED
6 DRAWER CABINET (F) (1036058) CONTINUED
2.
If a new work surface (Figure 6, Item 5) must be installed:
a.
Position work surface (Figure 6, Item 5), inished side up, on top of six drawer cabinet (F) (Figure 6, Item
6).
b.
Ensure work surface (Figure 6, Item 5) is lush with back side of cabinet with a two inch over hang on the
front side of cabinet. Work surface (Figure 6, Item 5) should over hang 15.00 inches on left and right side
of cabinet
c.
On inside of six drawer cabinet (F) (Figure 6, Item 6), mark eight hole placements in top of cabinet on
non-inished side of work surface (Figure 6, Item 5).
d.
After eight hole placement marks have been made, lip work surface (Figure 6, Item 5) over with non-
inished side up.
e.
On non-inished side of work surface (Figure 6, Item 5) at eight marked hole placements, center punch
and drill eight 5/16 inch holes to a depth of 3/4 inch.
f.
Return work surface (Figure 6, Item 5) inished side up, on top of six drawer cabinet (F) (Figure 6, Item
6).
3.
Align bolt holes in work surface (Figure 6, Item 5) with bolt holes on top of shelf cabinet (F) (Figure 6, Item 6).
4.
Install eight lag bolts (Figure 6, Item 1), eight lock washers (Figure 6, Item 2), six large lat washers (Figure 6,
Item 3), and two small lat washers (Figure 6, Item 4) securing work surface (Figure 6, Item 5) to six drawer
cabinet (F) (Figure 6, Item 6).
5.
Install four bolts (Figure 6, Item 8), eight lat washers (Figure 6, Item 4), four lock washers (Figure 6, Item
2), and four nuts (Figure 6, Item 9) securing two cabinet brackets (Figure 6, Item 7) to six drawer cabinet (F)
(Figure 6, Item 6).
6.
Install hardware attaching six drawer cabinet (F) (Figure 6, Item 6) to shelter loor IAW WP 0039 00, Cabinets
(F) Hardware (1036058), INSTALLATION.
7.
Install drawers, slides, and shelves as necessary IAW Drawers, Slides, And Shelves, INSTALLATION.
8.
Install kick plate IAW Kick Plate, INSTALLATION.
0038 00-14